PERT Estimated Time Formula

Whenever you’re in doubt whether that GANTT chart reflects accurately a task’s duration, here’s a formula that takes you one level above guestimation. Enter PERT (Program Evaluation and Review Technique) Estimated Time Formula:

shortest time + 4 x likely time + longest time
——————————————————————
6